Releasing capacity at a critical production bottleneck.

A two-week improvement project that increased throughput, moved minor repairs away from the machine and removed the need for a separate evening shift.

The opportunity

More output did not need more machine time.

A specialist engineering business was struggling to keep pace with demand at a critical production work centre. Overtime and an evening shift were being used, but capacity remained constrained. The review examined the complete process, from preparation and loading through machine processing and finishing, to identify where productive time was being lost.

2 weeksFrom initial review to implemented changes
Evening shiftRemoved from the operating model
Minor repairs movedCompleted before machine processing
Throughput upMore productive use of existing capacity

The review assessed seven operating scenarios. Detailed production quantities, part specifications and equipment data have been withheld to protect the client's confidentiality.

A specialist engineering and manufacturing business was struggling to keep pace with demand at a critical production work centre. The constraint was driving overtime and the use of an evening shift, but even with the additional hours, throughput was not sufficient to get ahead of the backlog.

The process combined several activities around one machine: bringing parts forward, loading, processing, minor repairs and offloading. The challenge was to increase the amount of productive work moving through the machine without simply extending operating hours or adding permanent headcount.

The work began on the shop floor. Time was spent observing the process from end to end, speaking with the people who operated and managed it, and recording timings and output. Historical production information from both shifts was reviewed to establish a realistic baseline and understand how the work centre was performing under normal operating conditions.

The review looked beyond the machine cycle itself. It considered the time spent moving parts into position, loading and unloading, minor repairs and preparing work for the next operation. It also took account of the fact that the evening team could be diverted to short-notice orders or issues elsewhere, so differences in shift output needed to be understood in context.

Seven operating scenarios were assessed, covering different batch sizes, part lengths and team configurations. The trials compared a two-person approach with options that used four people to keep material moving continuously through the work centre.

Each scenario was assessed on a consistent basis, using the available time in a shift and an agreed efficiency assumption. Minor repairs were separated from the machine cycle for the comparison so that the true productive capacity of the equipment could be understood. The analysis showed that a significant amount of capacity could be released by changing the sequence of work, rather than relying on additional shifts or simply putting more people around the machine.

The key finding was that the machine was being used for work that did not need to take place there. Minor repairs were being carried out at the machine, taking time away from the core processing activity. In addition, scrap parts were entering the process and consuming machine time despite having no productive value.

This meant the constraint was not just the machine's cycle time. The sequence of work was restricting the amount of useful output it could deliver. Moving minor repairs to an earlier stage and keeping scrap out of the machine process would allow the equipment to concentrate on suitable parts that were ready to be processed. The review also highlighted the importance of keeping the work centre supplied and considering the physical demands of handling longer and heavier items.

  • Minor repairs were moved away from the machine and completed before parts entered the process.
  • Scrap parts were stopped from entering the machine, eliminating time spent processing items that could not become saleable output.
  • The machine was refocused on its core processing activity, with suitable parts arriving ready for the operation.
  • The evening shift was removed, with the work reorganised around a day-shift operating model.

These were practical changes to the sequence and organisation of the work, rather than a capital investment or an increase in the number of shifts.

The changes were implemented and throughput increased. By moving minor repairs away from the machine and preventing scrap from entering the process, more of the available machine time was used for productive work. The business was able to remove the evening shift and operate without relying on a second shift to support the constrained work centre.

Removing the evening shift also removed the associated shift-premium costs and reduced the energy, heating and lighting needed to support the additional operating period. The machine was used for fewer hours overall, supporting lower wear and helping preserve equipment life.

The review, scenario assessment and implementation of the changes were completed in two weeks. No specific percentage increase is quoted here: the source analysis includes modelled scenario outputs, while the implemented improvement is described as a confirmed increase in throughput.

The Salvesen approach

Measure the work. Remove what adds no value. Release the capacity.

This project demonstrates how practical, evidence-led improvement can release capacity without investing in more equipment or extending the working day. By observing the real process, testing alternatives and changing where activities took place, the business increased throughput, removed unnecessary machine work and eliminated the need for an evening shift.